試卷年份2011年下半年
試題題型【單選題】
試題內(nèi)容

A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solutionat the meeting, The project manager should(  ).
A.Tell the customer that he will not address any problems
B.Tell the customer that the problem is not sufficiently defined to company to a solution
C.Collect as much information on the problem without committing hiscompany to a solution
D.Give the customer a range of solutions that might be acceptable to his company