試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(3)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(3)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The engineering department wants the project objective to be a lo percent improvement in throughput. The information technology department wants no more than five percent of its resources to be used on the project. Management, who is also your boss, wants the project team to decrease tax liability. The BEST thing you can do is:
A、put a plan together that meets all the objectives.
B、have these people get together and agree on one objective.
C、include the engineering and information technology objectives but hold further meetings regarding management's objective.
D、include only management's objective.