大决战电视剧在线观看央视6集|亚洲a级片|成人福利在线观看|方子传完整版未删减版电影,国产又黄又猛又粗又爽的视频,不安人在线观看未删减完整版 ,亚洲精品1区2区

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(5)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

You provide a project cost estimate to the project sponsor. He is unhappy with the estimate, because he thinks the price should be lower. He asks you to cut 15 percent off the project estimate. What should you do?
A、Start the project and constantly look for cost savings.
B、Tell all the team members to cut 15 percent from their estimates.
C、Inform the sponsor of the activities to be cut.
D、Add additional resources with low hourly rates.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容