大决战电视剧在线观看央视6集|亚洲a级片|成人福利在线观看|方子传完整版未删减版电影,国产又黄又猛又粗又爽的视频,不安人在线观看未删减完整版 ,亚洲精品1区2区

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

A project manager gets a call from a team member notifying the project manager that there is a variance between the speed of a system on the project and the desired or planned speed. The project manager is surprised because that performance measurement was not identified in planning. If the project manager then evaluates whether the variance warrants a response, the project manager is in what project management process?
A、Initiating
B、Executing
C、Monitoring and controlling
D、Closing


相關試題

推薦文章