大决战电视剧在线观看央视6集|亚洲a级片|成人福利在线观看|方子传完整版未删减版电影,国产又黄又猛又粗又爽的视频,不安人在线观看未删减完整版 ,亚洲精品1区2区

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2013下半年系統(tǒng)集成項(xiàng)目管理工程師考前密卷
考試中心《2013下半年系統(tǒng)集成項(xiàng)目管理工程師考前密卷》在線考試
試卷年份2013年下半年
試題題型【單選題】
試題內(nèi)容

The earned value technique is a commonly used method of performance measurement. It integrates project scope, schedule, and cost measures to help the project management team assess project performance. If a project's Cost Performance Index (CPI=EV/AC)  value less than 1.0, it means that ( )
A. the cost savings for work completed
B. the project is ahead of its planned schedule
C. the cost overrun for work completed
D. less work was completed than was planned


相關(guān)試題

推薦文章