第
72題: WhatdoesaCPIof80%mean().
A.Asofnowweexpectthetotalprojectcostof80%morethanplanned
B.Whentheprojectiscompleted,wewillhavespent80%more
C.Yourprojectisonlyprogressingat80%ofthatplanned
D.Yourprojectisonlygetting80centsoutofeveryRMBinvested
答案解析與討論:
www.bestofbreeders.com/st/6746660.html第
73題: Allthefollowingareroot-causeanalysistechniquesusedinqualitymanagementexcept().
A.Fishbonediagrams
B.Ishikawadiagrams
C.systemorprocessflowcharts
D.checklists
答案解析與討論:
www.bestofbreeders.com/st/6746725339.html第
74題: Acriticalpathforaprojectistheseriesofactivitiesthatdetermine()bywhichtheprojectcanbecompleted.
A.theearliesttime
B.thelatesttime
C.thetotaltime
D.thefreetime
答案解析與討論:
www.bestofbreeders.com/st/674688260.html